Monday, November 15, 2010

Day 30: Paving commences!, Post box benches, and Reed Screens continue.


Monday morning the first paving bricks from Corobrik arrived. Another truck load of sand was delivered, while quick meeting was held to decide on the paving pattern.

              
The river sand was distributed, and levelled...


 
...where after paving commenced. 



While the paving was being done the work on the reed screens continued.

 Schaiks continued the steel works on the screens.
The post box that was removed was cut up, and will be used as new benches.